Determination of Inter-Stage Idle Times in Scheduling Design of a Three Stage Zero Wait Batch Process

Amir Shafeeq, M.I. Abdul Mutalib, K.A. Amminudin and Ayyaz Muhammad

Abstract:
The present research proposes a novel approach based on matrix to determine the makespan of a batch process adopting zero wait transfer policy. The proposed approach uses simple mathematical formulae, applied on a matrix representing the batch process recipes according to a selected production sequence. Rearrangement of the matrix rows according to the varied production sequences possible for the specified batch process recipes enables the makespan to be determined for each sequence. Designer is then provided with the production sequence options with its corresponding makespan from which a selection could be made according to the process conditions.
PDF Fulltext XML References Citation Report Citation
How to cite this article:

Amir Shafeeq, M.I. Abdul Mutalib, K.A. Amminudin and Ayyaz Muhammad, 2008. Determination of Inter-Stage Idle Times in Scheduling Design of a Three Stage Zero Wait Batch Process. Journal of Applied Sciences, 8: 1706-1712.

DOI: 10.3923/jas.2008.1706.1712

URL: https://scialert.net/abstract/?doi=jas.2008.1706.1712

COMMENT ON THIS PAPER
 
 
 

 

 
 
 
 
 
 
 
 
 

 
 
 
 
 
 
 

Curve Bottom