ABSTRACT
According to the Hefei subway deep foundation pit engineering, this study expounds the pile-anchor supporting scheme of prestressed anchor cable layout optimization. Combined with the actual situation of engineering, numerical simulation was carryed out by using FLAC3D software. The four different layout of prestressed anchor cable is used for simulation analysis, Detailed to carry out the horizontal displacement of the pile and anchor axial force analysis, discuss the anchor cable layout optimization. Calculation results provide a reference for support scheme of similar large deep foundation pit.
PDF References Citation
How to cite this article
Donglin Wang, Jian Liang, Yusheng Jia and Xin Guo, 2013. Optimization of Combined Pile-anchor Supporting Schemes for Deep Foundation
Pit. Information Technology Journal, 12: 3034-3037.
DOI: 10.3923/itj.2013.3034.3037
URL: https://scialert.net/abstract/?doi=itj.2013.3034.3037
DOI: 10.3923/itj.2013.3034.3037
URL: https://scialert.net/abstract/?doi=itj.2013.3034.3037
REFERENCES
- He, S.M., X.G. Zhang and C.H. Wang, 2004. Study on mechanism of prestressed anchoring cable based on modified shear lag model. Chinese J. Rock Mech. Eng., 23: 2562-2567.
Direct Link - Xiong, Z.B., X.F. Liu, Q.Y. Wang and D.P. Gu, 2009. Inspection and monitoring analysis for anchor rope of pile-anchor retaining structure in deep foundation pit. J. Min. Metallurgical Eng., 29: 8-15.
Direct Link - Zhang, Q.X., D.K. Tong, Z.X. Xiong and L.J. Guo, 2006. Measurement and analysis on the stress in retaining pile and the force of anchor at a deep excavation of YA-AO building. J. Beijing Univ. Technol. Sci., 32: 76-82.
Direct Link